The Public Works Division’s director (works) additionally issued directions on this regard after receiving a communication from the joint secretary (price range) on January 10.
Because of the ongoing third wave of the COVID-19 pandemic, the Delhi authorities’s main focus is to strengthen medical and healthcare services. Therefore, the funding for a lot of development tasks has been lower, the officers stated on Thursday.
The revised price range allocation order issued by the PWD additionally requested officers to “strictly observe” economic system directions issued by the Finance Division of the Delhi authorities.
“The expenditure in the course of the present monetary yr mustn’t exceed the revised estimates (for) 2021-22. In case of a further expenditure, which can’t be additional postponed, the involved zones could ship proposal for re-appropriation of funds by offering matching financial savings,” the order said.
A few of the tasks for which funds have been curtailed are Barapullah Section-3 elevated hall; development of New Bypass street parallel to the Ring Street from Wazirabad to DND; flyover at Majnu Ka Tila-Metcalf Home crossing on Outer Ring Street; widening of bridges on NH-10 at Tri Nagar, Inderlok, Karampura; and built-in transit hall growth and avenue community between Punjabi Bagh flyover and Raja Backyard flyover.
Based on the revised allocation, the price range estimate for the Barapullah Section-3 undertaking has been halved from Rs 150 crore to Rs 75 crore.
The price range for the development of a flyover and elevated street at Karawal Nagar, Ghonda and Brijpuri junction on Mangal Pandey Marg in northeast Delhi has been lower down from Rs 100 crore to Rs 50 crore.
As towards an earlier allocation of Rs 20 crore for the development of a New Bypass street parallel to the Ring Street from Wazirabad to DND, the revised price range is barely Rs 1 crore.
The price range for restore, rehabilitation and upkeep of bridges and flyovers has additionally been diminished to Rs 15 crore from Rs 30 crore.
The federal government has additionally curtailed the price range for the development of foot overbridges from Rs 50 crore to Rs 40 crore.
Price range estimates for some essential tasks, just like the extension of the Ashram flyover as much as DND, have been elevated. The revised price range for the undertaking is Rs 80 crore, up from the sooner allocation of Rs 50 crore.